Considering the Appliance Warehouse Case Study, introduced in Week 1, and the project of planning and implementing a new Service Department as one of their product offerings. What tasks could you include in a WBS for Appliance Warehouse Case Study? What would be some possible risks for the implementation of the new Service Department?
Task No. Description Duration (Days) Predecessor Tasks
1 Reserve the meeting room 1
2 Order the marketing materials 9
3 Brief the managers 2
4 Send out customer emails 3
5 Upload program to the app store 3
6 Load the new software 2
7 Do a dress rehearsal 1